A change process model should include:
1 – The steps that should be taken to handle the change with any dependences or co-processing
defined, including handling issues and unexpected events
2 – Responsibilities; who should do what, including escalation
3 – Timescales and thresholds for completion of the actions
4 – Complaints procedures
A.
1, 2 and 3 only
B.
All of the above
C.
1 and 2 only
D.
1, 2 and 4 only