Which product is NOT created in the Managing a Stage Boundary process?
A. Benefits Review Plan
B. End Stage Report
C. Lessons Report
D. Exception Plan
2 Comments on “Which product is NOT created in the Managing a Stage Boundary process?”
abhisheksays:
Both A & C is correct
Petersays:
abhishek is wrong.
A is the only correct answer.
a Lessons Report is required, particularly for longer projects, where interim reviews of lessons, or the project itself, may benefit corporate or programme management.
Both A & C is correct
abhishek is wrong.
A is the only correct answer.
a Lessons Report is required, particularly for longer projects, where interim reviews of lessons, or the project itself, may benefit corporate or programme management.