Which P3O capability is MOST likely to lead to unviable projects being stopped at the initial
investment gate?

A.
Tracking of progress on programmes against key outcomes
B.
Selection of the right programmes and projects via an established structure
C.
Identification of potential duplication of scope or double counting of benefits
D.
Coordinated change control process across multiple projects and business operations