What is the most likely reason for the pausing of some of the SyncIQ jobs?

A customer created eight SyncIQ policies on a 6-node Isilon cluster that all start at midnight. They are running
into issues where several jobs are paused while others are still running. This is delaying the overallreplication
of data. What is the most likely reason for the pausing of some of the SyncIQ jobs?

PrepAway - Latest Free Exam Questions & Answers

A.
An Isilon cluster can only have five concurrent SyncIQ jobs running at the same time.

B.
An Isilon cluster can only have one SyncIQ job running at any one time.

C.
SyncIQ only allows one job per node; this clustercan only run six SyncIQ jobs concurrently.

D.
SyncIQ staggers the start of all SyncIQ jobs; jobs after the first job are delayed.