After acquiring a company 300 hundred miles from their current office, a customer has asked EMC
to help design a single-hop application recovery plan. After careful analysis of the workload and
available bandwidth, SRDF/AR was selected as the solution.
If the SRDF/AR cycle time is set to 60 minutes, what is the maximum potential data loss?

A.
1 hours of data
B.
1.5 hours of data
C.
2 hours of data
D.
3 hours of data
Explanation:
C
0
0