Applications of different criticality have been deployed on a collection of virtual servers. In an effort to save cost, a business continuity plan has been devised to provide half the number of physical servers to host the virtual machines at the disaster recovery site.
What is a possible outcome if a disaster were to occur at the primary site?
A.
Applications cannot be resolved
B.
Application data is inaccessible
C.
Application data is lost
D.
Application performance is degraded
Explanation:
Topic: Describe planning and design considerations for virtualized compute and application environments
Training: Mod 3, Designing for Virtualized and Cloud Environments