What happens when data is being written to track 1000 in the 4th target?

On a VMAX using TimeFinder VP Snap five sessions have been activated against a single data
source at different times so each session contains a different point in time snapshot of the data on
the source. Track 1000 was overwritten after the last session was activated.
What happens when data is being written to track 1000 in the 4th target?

PrepAway - Latest Free Exam Questions & Answers

A.
The original data of track 1000 will remain unchanged for targets 1, 2, 3 and 5.
Target 4 will get its own modified copy of that track.

B.
The original data of track 1000 will remain unchanged for targets 1, 2 and 3.
Targets 4 and 5 will get their own modified copy of that track.

C.
The original data of track 1000 will remain unchanged for targets 1, 2 and 3.
Target 4 will get its own modified copy of that track.
Target 5 will get its own copy of the original track 1000.

D.
Targets 1, 2 and 3 will get their own copy of the original track 1000.
Track 4 will get its own modified copy of that track.
The original data of track 1000 will remain unchanged for target 5.

Explanation:

3 Comments on “What happens when data is being written to track 1000 in the 4th target?

  1. Chris says:

    Answer is A not C. We are updating track 1000 on target 4 only, this doesn’t change the the other targets at all. So only target 4 will get its own copy of the track