If the SRDF/AR cycle time is set to 60 minutes, what is the maximum potential data loss?

After acquiring a company 300 hundred miles from their current office a customer has asked EMC to help architect a single hoop application recovery plan. Aftercarefulanalysis of the workload and available bandwidth, SRDF/AR was selected as solution.

If the SRDF/AR cycle time is set to 60 minutes, what is the maximum potential data loss?

PrepAway - Latest Free Exam Questions & Answers

A.
1 hour of data

B.
15 hours of data

C.
2 hours of data

D.
3 hours of data