You are the project manager for a construction project. The project involves casting of a column in
a very narrow space. Because of the lack of space, casting is highly dangerous. High technical
skill will be required for casting that column. You decide to hire a local expert team for casting that
column. Which of the following types of risk response are you following?

PrepAway - Latest Free Exam Questions & Answers

A.
Transference

B.
Mitigation

C.
Avoidance

D.
Acceptance

Explanation: