Which of the following would be the LAST area to shut down?

A company is implementing a private cloud infrastructure and is testing its high availability components. In a planned outage test, all systems will be shut down sequentially. Which of the following would be the LAST area to shut down?

PrepAway - Latest Free Exam Questions & Answers

A.
Offsite mirror

B.
Networking

C.
Hypervisors

D.
Storage