Which of the following would be done FIRST in order to develop this plan?

An administrator is creating a business continuity plan. Which of the following would be done FIRST
in order to develop this plan?

PrepAway - Latest Free Exam Questions & Answers

A.
Setup replication on all SANs

B.
Classify systems

C.
Locate an offsite facility for failover

D.
Create an architecture plan for all systems