Which of the following methods should the project manager select to investigate?

The schedule estimates for a particular work package that is underway were not properly considered and the timescales are too tight. Which of the following methods should the project manager select to investigate?

A.
PDM

B.
SPI and SV

C.
CPM

D.
Issues log