A project manager who is part of a global team wants to have a team building meeting and decides
to Mold a video conference. Which of the following is MOST likely to be the main challenge that
influences this decision?
![PrepAway - Latest Free Exam Questions & Answers](https://www.briefmenow.org/img/pa5.jpg)
A.
Geographical factors
B.
Language barriers
C.
Cultural differences
D.
Technology factors