PrepAway - Latest Free Exam Questions & Answers

The scope of activity as described in the statement of …

A project lead is reviewing the statement of work for an upcoming project that is focused on identifying potential weaknesses in the organization’s internal and external network infrastructure. As part of the project, a team of external contractors will attempt to employ various attacks against the organization. The statement of work specifically addresses the utilization of an automated tool to probe network resources in an attempt to develop logical diagrams indication weaknesses in the infrastructure.
The scope of activity as described in the statement of work is an example of:

PrepAway - Latest Free Exam Questions & Answers

A.
session hijacking

B.
vulnerability scanning

C.
social engineering

D.
penetration testing

E.
friendly DoS


Leave a Reply