Which of the following metrics demonstrates to a project manager if a pro
ject is overspending or underspending?
A. EAC
B. BAC
C. CPI
D. ETC
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 231