Which of the following is the BEST form of communication to address this issue?
A project manager has an initial problem with a remote team members performance. Which of the
following is the BEST form of communication to address this issue?
How many communication channels are now existent?
The project manager has three stakeholders with whom they need to communicate (not including
the project manager). There are six channels of communication. A new stakeholder has been
added to the project that the project manager needs to communicate with. How many
communication channels are now existent?
The formal process that must be performed at the end of the project to provide the final inspection of the pro
The formal process that must be performed at the end of the project to provide the final inspection
of the product is called:
Who did the project manager contact?
A manager and the head of engineering discuss a change to a major work package. After the
meeting, the project manager contacts a third person and tells them to complete the paperwork to
make the change. Who did the project manager contact?
Which of the following will MOST likely be affected by these circumstances?
A project manager is managing the delivery of a project awarded under a fixed-cost contract. The
project cost was poorly planned and underestimated, but the projects overall scope and deadline
cannot change. Failure to deliver the project is not an option. Which of the following will MOST
likely be affected by these circumstances?
Which of the following is created during the initiation phase?
Which of the following is created during the initiation phase?
Which of the following is the MOST common precedence dependency type?
Which of the following is the MOST common precedence dependency type?
Which of the following correctly identifies the application of a projects quality management plan?
Which of the following correctly identifies the application of a projects quality management plan?
Which of the following is the effect of triple constraint on a project?
Which of the following is the effect of triple constraint on a project?
Which of the following estimates should be given to the project sponsor?
A project manager is two weeks into a project when an unexpected delay occurs. Material that is
needed to complete the project could be available in three business days; however, the project
team believes that estimate is unrealistic and that it will take five business days for the material to
arrive. The project manager was informed by another employee in the material company that it
could take up to thirteen days to receive the materials. Which of the following estimates should be
given to the project sponsor?