Which of the following is an appropriate reason for not starting the project?
A company manager has turned in project objectives, and requests that the project manager start
the project immediately. The project manager informs the company manager that the project
cannot be started. Which of the following is an appropriate reason for not starting the project?
Which of the following is the FIRST technique the project manager can use to define their roles?
Project team members are confused about their roles on a project. Which of the following is the
FIRST technique the project manager can use to define their roles?
Which of the following is the purpose of a post-project review?
Which of the following is the purpose of a post-project review?
Which of the following is the MOST likely cause of the reports?
The project manager has outsourced a call center to a company in another region. The project
manager receives reports that customers sometimes cannot hear the instructions given by call
center employees. Which of the following is the MOST likely cause of the reports?
Which of the following estimating types requires the MOST effort when creating a work breakdown structure (WBS
Which of the following estimating types requires the MOST effort when creating a work breakdown
structure (WBS)?
Which of the following is a method of transferring the risk?
A project has been delayed due to an ongoing labor dispute. The project sponsor asks the project
manager to transfer the risk to complete the project on time. Which of the following is a method of
transferring the risk?
Which of the following steps should the project manager take to resolve the conflict?
Several team members have criticized the project manager for requesting that they work overtime
in order to complete a project on time. Which of the following steps should the project manager
take to resolve the conflict?
Which of the following are common causes of project team conflict?
Which of the following are common causes of project team conflict? (Select Two).
Which of the following would be included in a project scope document?
Which of the following would be included in a project scope document? (Select Three).
Which of the following is the NEXT step that the project manager should take?
A project change is approved by the Change Control Board that modifies the project scope. Which
of the following is the NEXT step that the project manager should take?