Which of the following is the MOST likely action the project manager should take?
A team member on a project uncovers a minor risk with the quality of a purchased component. The team uses their combined expert judgment to determine that the risk to the deliverable is very low. Which of the following is the MOST likely action the project manager should take?
Which of the following methods should the project manager select to investigate?
The schedule estimates for a particular work package that is underway were not properly considered and the timescales are too tight. Which of the following methods should the project manager select to investigate?
Which of the following shows the number of communication channels for a team with twelve stakeholders?
Which of the following shows the number of communication channels for a team with twelve stakeholders?
Which of the following would a project manager do NEXT after selecting a vendor for a project?
Which of the following would a project manager do NEXT after selecting a vendor for a project?
The project manager is using which of the following risk response techniques to resolve the issue?
An important team member will not be available to complete a project. The project manager selects a new team member and trains the new team member on the project tasks. The project manager is using which of the following risk response techniques to resolve the issue?
By completing the lessons learned during project closure, the project manager can:
By completing the lessons learned during project closure, the project manager can:
Which of the following risk responses is the project manager using?
Several project tasks cannot be completed because local resources are not available. The project manager has to outsource the work to find qualified resources. Which of the following risk responses is the project manager using?
Which of the following risk responses is the project manager using?
A hurricane is forecasted near the corporations call center. The project manager has arranged for a redundant call center in another location to accept calls if the corporate call center is unable to receive calls. Which of the following risk responses is the project manager using?
Which of the following should the project manager do to make the project status meetings more productive? (Sel
A project manager notices that status meetings are poorly attended and that one or two team members try to dominate the meetings. Which of the following should the project manager do to make the project status meetings more productive? (Select Two).
Which of the following communication mediums would BEST facilitate the goal?
A project manager is implementing a new community park and wants to build public support. Which of the following communication mediums would BEST facilitate the goal?