Which YARN daemon or service negotiates map and reduce Containers from the Scheduler,
tracking their status and monitoring for progress?
A.
ResourceManager
B.
ApplicationMaster
C.
NodeManager
D.
ApplicationManager
Explanation:
http://docs.hortonworks.com/HDPDocuments/HDP2/HDP-2.1-latest/bk_using-apachehadoop/content/yarn_overview.html
B. Application Master. This negotiates containers with the Resource manager.
0
0
Correct answer is B