Which of the following BEST utilizes OOAD artifacts to manage a project team?

Which of the following BEST utilizes OOAD artifacts to manage a project team? Divide the project
staff into:

PrepAway - Latest Free Exam Questions & Answers

A.
teams according to packages, schedule efforts by use cases across the teams as appropriate.

B.
small teams, distribute an appropriate number of use cases to each person, schedule the team
efforts by the use cases.

C.
teams according to use cases, assign ownership of each use case to one developer, schedule
efforts by use case with multiple developers working on a use case as appropriate.

D.
teams along the lines of the software architecture layers, distribute use cases to the team that
is most responsible for the use case functionality.