Scenario: The network engineer has created a monitor and bound it to a service group
containing four web servers to verify that the web application responds. During routine
maintenance one of the web servers is shut down; however, the server state remains UP
and user requests are still attempting to communicate with the server. What could be
causing this problem?

PrepAway - Latest Free Exam Questions & Answers

A.
The monitor is not bound at the correct bind point.

B.
Health monitoring is disabled for the service group.

C.
The server has been disabled.

D.
The NetScaler configuration has not been saved since before the monitor was bound.

Explanation: