Which two service components are part of the plan phase? (Choose two

Which two service components are part of the plan phase? (Choose two.)

PrepAway - Latest Free Exam Questions & Answers

A.
Proof of Concept

B.
Operations Readiness Assessment

C.
Site Readiness Assessment

D.
Proposal Development

E.
Account Planning

Explanation:

During the Plan phase of the Network Lifecycle, the project team needs to assess the current network, site and operations readiness which will aid in the design of the proposed technologies. In addition, the project team needs to plan for project management resources, as well as assess security vulnerability of the current system.