PrepAway - Latest Free Exam Questions & Answers

Which three test elements need to be documented when producing a business readiness test plan? (Choose three

.Which three test elements need to be documented when producing a business readiness test plan? (Choose three.)

PrepAway - Latest Free Exam Questions & Answers

A.
Feature Configuration Tests

B.
EndPoint Migrations Tests

C.
Business Critical Application Tests

D.
Third-Party Operations and Network Management Application and Integration Tests