Which three components and tasks should be considered while planning the site survey? (Choose three

Which three components and tasks should be considered while planning the site survey? (Choose three.)

PrepAway - Latest Free Exam Questions & Answers

A.
Determine the project scope, type of deployment, timeline, scale, budget, and users

B.
Determine project stakeholders

C.
Determinecustomer training requirements

D.
Determine AP and controller placement

E.
Determine the customer applications that the network will support

F.
Determine radiospectrum and channel allocation

G.
Schedule customer end user interviews