In the plan phase, which of the following is a deployment project management task?

In the plan phase, which of the following is a deployment project management task?

PrepAway - Latest Free Exam Questions & Answers

A.
develop backup/recovery plan

B.
obtain and review security procedures

C.
analyze current infrastructure and propose new solution

D.
review logical, system, and user design

E.
collect and verify project management plan requirements

Explanation:

Reference: Page 2, Diamond 1, of the “Plan, Deployment Project Management”, Web Training for Cisco Life Service Express
Not A: This is correct in the beginning of the design phase.