In the implement phase, project planning comprises which of the following tasks?

In the implement phase, project planning comprises which of the following tasks?

PrepAway - Latest Free Exam Questions & Answers

A.
Install, configure, and provision core products

B.
Confirm project and milestone dates, as well as project and cutover roles and responsibilities

C.
Update and document logical and physical topology maps and serial numbers

D.
Confirm deployment team, craft project plan,create communication and escalation plans