PrepAway - Latest Free Exam Questions & Answers

Which command would be used on the FastIron to reallocate power back to the available power budget, while stil

A powered device connected to a Brocade FastIron device has been auto discovered and
classified as a class-3 PoE device. However, its power consumption is only 10 watts. Which
command would be used on the FastIron to reallocate power back to the available power budget,
while still providing all the necessary power to the powered device?

PrepAway - Latest Free Exam Questions & Answers

A.
no legacy-inline-power

B.
inline power power-by-class 2

C.
inline power priority 2

D.
inline power power-limit 11000

One Comment on “Which command would be used on the FastIron to reallocate power back to the available power budget, while stil


Leave a Reply