What are two considerations when developing this migration plan?

A customer is migrating their FICON servers and storage from an M-Series SAN that is end of
lease to a new SAN using two Brocade DCX 8510-8 Backbones with optical ICLs. They also want
to intermix the FICON and zLinux traffic on the same DCX 8510-8 Backbone. What are two
considerations when developing this migration plan? (Choose two.)

PrepAway - Latest Free Exam Questions & Answers

A.
ICL connectivity counts as a hop of concern.

B.
The FICON and zLinux traffic must be configured in separate zones.

C.
FICON licenses must be procured for each DCX 8510.

D.
Virtual Fabrics should be used with FC16-48 port blades.