PMI Exam Questions

Which tools are at the manager’s disposal?

The project manager at an organization has just realized that some of the engineering staff has
been allocated to project Y and will not be available to finish task X. The project manager has also
discovered that at the current pace, it will not be possible to complete the project on time. Due to
cost constraints, hiring more work force is not a viable option. Which tools are at the manager’s
disposal?

A.
Resource leveling and fast tracking

B.
Fast tracking and crashing

C.
Crashing and applying leads and lags

D.
Scheduling tools and applying leads and lags