which process is a project manager identified and given the authority to apply resources to project seenagape 10 years ago In which process is a project manager identified and given the authority to apply resources toproject activities? A.Acquire Project Team B.Develop Project Management Plan C.Manage Project Execution D.Develop Project Charter ← Previous question Next question →