Which of the following documents allows the project manager to assess risks that may require near te seenagape 9 years ago Which of the following documents allows the project manager to assess risks that may requirenear term action? A.Probability and impact matrix B.Contingency analysis report C.Risk urgency assessment D.Rolling wave plan ← Previous question Next question →