Which of the following documents allows the project manager to assess risks that may require near te

Which of the following documents allows the project manager to assess risks that may require
near term action?

A.
Probability and impact matrix

B.
Contingency analysis report

C.
Risk urgency assessment

D.
Rolling wave plan