Which process involves aggregating the estimated costs of the individual schedule activities or work admin 11 years ago Which process involves aggregating the estimated costs of the individual schedule activities or work packages? A.Cost baseline B.Cost forecasting C.Cost variance D.Cost budgeting ← Previous question Next question →