Which estimating technique uses the actual costs of previous similar projects as a basis for estimat seenagape 10 years ago Which estimating technique uses the actual costs of previous similar projects as a basis forestimating the costs of the current project? A.Analogous B.Parametric C.Bottom-up D.Top-down ← Previous question Next question →