Which of the following techniques may be applied to reevaluate the schedule?

A project manager needs to deliver the project 2 weeks before the planned date without changing
the scope. Which of the following techniques may be applied to reevaluate the schedule?

A.
What-if scenario analysis

B.
Critical chain method

C.
Schedule crashing

D.
Resource leveling