Which Activity Duration Estimating technique incorporates additional timing for contingency purposes seenagape 9 years ago Which Activity Duration Estimating technique incorporates additional timing forcontingency purposes? A. Analogous Estimating B. Expert Judgment C. Optimistic Estimates D. Reserve Analysis ← Previous question Next question →