which corrective action will be taken to prevent exceeding the specification limits?

When a control chart is used to monitor performance of a process, which of the
following will be set by the project manager and the appropriate stakeholders to
reflect the point(s) at which corrective action will be taken to prevent exceeding the
specification limits?

A.
Upper and lower control limits

B.
Upper and lower specification limits

C.
Process mean

D.
Data points