What time management activity should be done NEXT?

The project manager has performed schedule network analysis, compressed the schedule, and completed a Monte Carlo analysis. What time management activity should be done NEXT?

A.
Update resource requirements

B.
Recommend corrective actions

C.
Estimate Activity Durations

D.
Create a milestone list