PMI Exam Questions

The BEST approach to crashing would also include looking at the:

In attempting to complete the project faster, the project manager looks at the cost associated with crashing each activity. The BEST approach to crashing would also include looking at the:

A.
Risk impact of crashing each activity.

B.
Customer’s opinion of which activities to crash.

C.
Boss’s opinion of which activities to crash and in which order.

D.
Project life cycle phase in which the activity is due to occur.