PMI Exam Questions

what is the team’s velocity?

Following chart lists stories for a release of an Agile project;

If the team completes Story A, Story B, and 50% of Story C for the first iteration, what is the
team’s velocity?

A.
9

B.
10

C.
12

D.
15