what is the team’s velocity? seenagape 10 years ago Following chart lists stories for a release of an Agile project; If the team completes Story A, Story B, and 50% of Story C for the first iteration, what is theteam’s velocity? A.9 B.10 C.12 D.15 ← Previous question Next question →