PMI Exam Questions

how many iterations will be needed to complete all of the stories?

The following chart lists stories for a release of an Agile project:

If the velocity of the team is 10, how many iterations will be needed to complete all of the
stories?

A.
3

B.
4

C.
5

D.
7