What is the lowest level in the WBS at which the cost and activity durations for the work can be rel admin 11 years ago What is the lowest level in the WBS at which the cost and activity durations for the work can be reliably estimated and managed? A.Work product B.Work package C.Project deliverable D.Scope baseline ← Previous question Next question →