What is the expected activity cost for a project having a most likely cost of $140, a best case scen admin 11 years ago What is the expected activity cost for a project having a most likely cost of $140, a best case scenario of $115, and a worst case scenario of $165? A.$115 B.$138 C.$140 D.$165 ← Previous question Next question →