The project manager calculated a schedule performance index of 0.8 and a cost performance index of 1.1 for the project. What is the actual status of this project?

A.
Behind schedule and over budget

B.
Behind schedule and under budget

C.
Ahead of schedule and under budget

D.
Ahead of schedule and over budget