The Process Group that involves coordinating people and…

The Process Group that involves coordinating people and resources, as well as integrating and performing the
activities of the project in accordance with the project management plan is known as:

A.
Initiating.

B.
Planning.

C.
Executing.

D.
Monitoring and Controlling.