Which of the following are inputs to the Plan Procurements process?

A.
Risk register, scope baseline, enterprise environmental factors, organizational process assets, project
schedule

B.
Risk register, scope baseline, make-or-buy decisions, organizational process assets, project schedule

C.
Project management plan, qualified seller list, contract, enterprise environmental factors, teaming
agreements

D.
Project management plan, qualified seller list, contract, make-or-buy decisions, teaming agreements