PMI Exam Questions

The iterative process of increasing the level of detail…

The iterative process of increasing the level of detail in a project management plan as greater amounts of
information become available is known as:

A.
Continuous improvement.

B.
Predictive planning.

C.
Progressive elaboration.

D.
Quality assurance.