PMI Exam Questions

which resources are tied to work packages?

Which grid shows which resources are tied to work packages?

A.
Work breakdown structure (WBS)

B.
Responsibility assignment matrix (RAM)

C.
Project assignment chart

D.
Personnel assignment matrix