PrepAway - Latest Free Exam Questions & Answers

Tag: Exam PMI-SP

Exam PMI-SP: PMI Scheduling Professional

What law of economics would prevent Harry from exponentially adding labor to the project work in an effort to

Harry is the project manager of a large network installation project. This project requires Harry to
add network cable to each office and cubicle of a 14-story office building. Harry will receive a
bonus for good time and cost performance in this project. What law of economics would prevent
Harry from exponentially adding labor to the project work in an effort to complete the work in a
very small amount of time?

What else should Fred do to account for the twenty-four hours of cure time?

Fred is the project manager of a hotel restoration project. The hotel has 456 rooms. All rooms
need to be primed and painted. Before each room can be painted, the primer must cure for twenty-four hours. Fred has arranged these tasks with a finish to start relationship between the priming
and the painting. What else should Fred do to account for the twenty-four hours of cure time?

Which of the following are the necessary inputs?

You work as a project manager for Honeywell Inc. You have been distributing performance
information, including status reports, progress measurement, and forecasts to various
stakeholders. A trainee of this company wants to know what are the inputs for generating
performance reports. Which of the following are the necessary inputs? Each correct answer
represents a part of the solution. Choose two.

What part of your project has the largest variance?

You are the project manager of the GHY project. Your project has a BAC of $675,000 and is forty
percent complete though you were supposed to be forty-five percent complete. Due to some
errors early in the project, you had to spend $278,000 of your project’s budget to reach this point.
Management is asking for a variance report. What part of your project has the largest variance?

What project Management process are you working with when you create a new target schedule?

You work as a project manager for BlueWell Inc. Some of the activities in your project are not
being completed on time. You reviewed these activities with your project team and discovered that
the time estimates for the project are much more aggressive than what they are actually
experiencing in the completion of the activities. You elect to create a new schedule for the project.
What project Management process are you working with when you create a new target schedule?


Page 28 of 31« First...1020...2627282930...Last »