What component of the change control system would review the proposed changes’ impact on the features an

[tagged]
Henry is the project manager of the QBG Project for his company. This project has a budget of
$4,576,900 and is expected to last 18 months to complete. The CIO, a stakeholder in the project,
has introduced a scope change request for additional deliverables as part of the project work.
What component of the change control system would review the proposed changes’ impact on the
features and functions of the project’s product?

what type of a grid or model should you create based on these conditions?

[tagged]
You are the project manager for BlueWell Inc. Your current project is a high priority and high
profile project within your organization. You want to identify the project stakeholders that will have
the most power in relation to their interest on your project. This will help you plan for project risks,
stakeholder management, and ongoing communication with the key stakeholders in your project.
In this process of stakeholder analysis, what type of a grid or model should you create based on

these conditions?

What risk response is this?

Lisa is the project manager of the FKN project for her organization. She is working with Sam, the
CIO, to discuss a discount the vendor has offered the project based on the amount of materials
that is ordered. Lisa and Sam review the offer and agree that while their project may qualify for the
discounted materials the savings is nominal and they would not necessarily pursue the savings.
Lisa documents this positive risk response in the risk register. What risk response is this?

Why is it necessary to include the project’s cost management plan in the preparation for the quantitat

You are preparing to complete the quantitative risk analysis process with your project team and
several subject matter experts. You gather the necessary inputs including the project’s cost
management plan. Why is it necessary to include the project’s cost management plan in the

preparation for the quantitative risk analysis process?