PrepAway - Latest Free Exam Questions & Answers

Tag: Exam PMI-RMP

Exam PMI-RMP: PMI Risk Management Professional

What is the estimate at completion?

You are the project manager of the NHJ project for your company. This project has a budget at
completion of $1,650,000 and you are 60 percent complete. According to the project plan,
however, the project should be 65 percent complete. In this project you have spent $995,000 to
reach this point of completion. There is a risk that this project may be late so you have taken some
measures to recover the project schedule. Management would like to know, based on current
performance, what the estimate at completion for this project will be. What is the estimate at
completion?

Which risk analysis approach can Frank use to create an approach to make decisions in the presence of uncertai

[tagged]
Frank is the project manager of the NHQ project for his company. Frank is working with the project
team, key stakeholders, and several subject matter experts on risks dealing with the new materials
in the project. Frank wants to utilize a risk analysis method that will help the team to make
decisions in the presence of the current uncertainty surrounding the new materials. Which risk
analysis approach can Frank use to create an approach to make decisions in the presence of
uncertainty?

What risk response has been given in this project?

Jane is the project manager of the GBB project for her company. In the current project a vendor
has offered the project a ten percent discount based if they will order 100 units for the project. It is
possible that the GBB Project may need the 100 units, but the cost of the units is not a top priority
for the project. Jane documents the offer and tells the vendor that they will keep the offer in mind
and continue with the project as planned. What risk response has been given in this project?

what type of risk response?

Tracy is the project manager of the NLT Project for her company. The NLT Project is scheduled to
last 14 months and has a budget at completion of $4,555,000. Tracy’s organization will receive a
bonus of $80,000 per day that the project is completed early up to $800,000. Tracy realizes that
there are several opportunities within the project to save on time by crashing the project work.
Crashing the project is what type of risk response?


Page 3 of 2812345...1020...Last »